    g'day all.
    Now i've bought my shed I have to put a slab down. The shed guy said it's cheaper to do the boxing myself, order the concrete and get a couple of concreters in and pay them day rates.
    Any one tell me how to box up a 9m x 7.5m x 100mm slab. The ground is classified Class A (sandy soil which the Architect says is the best to put slabs on).

    Cheers. Any advice gratefully received.
    If you never made a mistake, you never made anything!


  2. #2
    Join Date
    Nov 2004
    Location
    Port Pirie SA
    Age
    53
    Posts
    0
    Post Thanks / Like

    Default

    If you can hire some form work, as you need at least 33m of it... Or you could buy some 100-150mm "C" section and use that, the 100mm would be cheaper.(I got 150mm, you can always bury in ground 2" for 4" concrete)
    They come in 7.5m lenghts so you will need about 5, 1 of them will need to be cut. Drill 2 holes in them for pegs on the sides, this will hold them inplace while the main holding pegs are positioned on the outside(1 peg every 500mm).
    Then lay the plastic in and then coat the C section in oil... before putting the mesh down!
    This will give you reusable form work, that will outlast traditional marine ply form work... or can be reused as its intended purpose to build a lean-too out of... extra wood storage!
    Hint!, work out where your going to put your power box/board and put a 90° conduit bend in under the form work, so when the power cables are run it'll be a neat job... can do with water/sewage for hand basin too!
    ....................................................................

  3. #3
    Join Date
    Jul 2004
    Location
    Sale
    Age
    69
    Posts
    559
    Post Thanks / Like

    Default

    I use pine commons 90 x 45 at about $1.00 per metre, its pretty much useless afterwards but with plenty of pegs and bracing its fine if boxing up on level ground. Besides it burns ok in winter, but you might try the hire places it will work out dearer most likely but you would find it easier to keep the edges straight.

    John.

  4. #4
    Join Date
    Nov 2004
    Location
    tasmania
    Age
    61
    Posts
    154
    Post Thanks / Like

    Default

    Dont skimp on pegs to keep your formwork straight .
    Wet concrete is very heavy and you'll do yourself no favours if it bows or worse .
    Its really very easy if you know how so dont feel overwelmed by it . If you really want to save money buy yourself a good plastic float and a steel trowel , put on a bbq for 2 friends and do it yourself . Its not a big slab and any handyman/woman could do it with the right advice and also dont feel scared to ask the concrete truck driver for advice . Is it to wet/dry . They are very helpful and have seen many slabs poured so they know more than us . Mine even helped screed the concrete ! The formwork is the most important part and if you are capable of that you are more than capable of pouring the slab completly .
    Regards
    Rick
    uhm , where am I ?

  5. #5
    Join Date
    Nov 2005
    Location
    West Gippsland, Vic
    Age
    73
    Posts
    394
    Post Thanks / Like

    Default The Slab

    Quote Originally Posted by rick_rine
    Dont skimp on pegs to keep your formwork straight .
    Wet concrete is very heavy and you'll do yourself no favours if it bows or worse .
    Its really very easy if you know how so dont feel overwelmed by it . If you really want to save money buy yourself a good plastic float and a steel trowel , put on a bbq for 2 friends and do it yourself . Its not a big slab and any handyman/woman could do it with the right advice and also dont feel scared to ask the concrete truck driver for advice . Is it to wet/dry . They are very helpful and have seen many slabs poured so they know more than us . Mine even helped screed the concrete ! The formwork is the most important part and if you are capable of that you are more than capable of pouring the slab completly .
    Regards
    Rick
    Thanks for all the tips and advice guys. Its going to be a DIY job (BBQ and Beer for the labourers - if you're in Tassie during January and get tired of the fishin' :eek: and swimmin' let me know and I'll get some extra Cascade and Porterhouse steaks)
    If you never made a mistake, you never made anything!


Similar Threads

  1. Concrete Slab Insulation
    By dallas in forum CONCRETING
    Replies: 10
    Last Post: 11th June 2007, 07:05 PM
  2. Grinding a concrete slab
    By vGolfer in forum CONCRETING
    Replies: 19
    Last Post: 25th August 2005, 11:08 PM
  3. Extending a concrete slab
    By princhester in forum CONCRETING
    Replies: 8
    Last Post: 24th July 2005, 08:49 PM
  4. Flooring Options on Cement Slab?
    By dallas in forum FLOORING
    Replies: 8
    Last Post: 7th December 2004, 08:13 AM

Tags for this Thread

Bookmarks

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •