Originally Posted by
bricks
Just asking why you absolutely need to have a void under that slab?
Surely the best option would be to put plastic water barrier ( forte-con) around the inside of the brickwork and back fill with sand?
Before I demolished them, the old back steps were filled with sand and bricks and ANTS. Little buggers, there were millions of them and we could never kill the nest, also with what I now know about protecting against termites, it was a good point of undetected entry for them.
I left a void that will have an opening door to be able to inspect for nasties and spray with the annual pest control.
As for cureing time, the number that usually gets thrown around is 28 days, you could cover the top of the slab with plastic after you pour, This helps to stop the top drying out faster than the bottom and prevents cracking in the surface, ( it cures evenly).
And make sure you insulate the concrete slab from the side of your house.
I put 10mm expansion joint between the brickwork of the step and the house and plan to do the same or leave a gap between the slab and the framework, is this what you mean?
Nice brickwork by the way.
Thanks I'm slow but getting good at it now.