Originally Posted by
rwbuild
Some years ago when I was supervising for a project builder had a job that backed onto a reserve. House was peged, concreter starts and because there was a reasonable amount of fill at the back of the house after creating the platform for the slab it had to be piered. Concreter merrily drilling away , hits something hard, not unusual, probably a rock, puts rock auger on rig, punches down, then auger drops 1.0m instantly then hard again. He immediately what it was, sewer main, main truck line for that portion of the subdivision. MWSDB had already approved the plans and not in the zone of influence. Yeah, right, when they laid the main their own surveyor had stuffed up big time. It affected about 10 houses and it cost the MWSDB big $'s for those 10 houses when they were built, they opted to pier and bridge the main, was cheaper than doing a new main and they accepted all responsibility indefinitely.