Sequence Of Operations For Architraves & Skirts
Hi,
As I have mentioned elsewhere we are having our laundry/toilet renovated presently and yet again we are having problems with one tradesman blaming another for the way the job has been done so far. The person to really blame is the manager of the company who obviously has too many projects on the go to be able to give clear instructions and get the right tradesperson in at the correct time at our abode.
For instance should the plastering be completed prior to the architraves and skirts being fitted?
Should the plumber (who came in prior to the carpenter fitting the architraves and skirts) have completed doing his tasks prior to the chippie coming in?
I will lay the vinyl floor tiles but I was advised that this should be done after the skirts are in place in other words the new skirting doesn't lay on top of the new tiles?
I would appreciate anyone's thoughts/advice who may have been through a similiar situation previously.
Cheers
MH