Hi,
So I have some small footings dug, which is near 1m3 in volume in total needing to be filled. Does wet mixed concrete have less volume than when it was just a dry mix? ie if 1m3 of volume needs to be filled with concrete is it approximate 1.5m3 of dry mix material requied (grave, sand and cement combined)?
So if I were using 14 bags of cement (approximate 0.28m3) , I would need appoxt 1.22m3 of sand&gravel mix to fill a void of 1m3?