F5 instead of MGP10 in engineering plan
Hello Experts,
My builder has used F5 timber instead of MGP10 which was on the engineering plan. When this was picked up during a private inspection. The builders have not notified us of anything in writing along with the unchanged engineering plans. Is this legal for them to swap the timber as per their wish without the engineering approval? I've been advised on a different platform that it is probably ok to swap F5 to MGP10 but not the other way round. Frame stage is now complete with roof tiles on and bricks ready to go soon and I am super concerned not knowing the basics around it. Timber schedule from engineering attached for reference.
Greatly appreciate some adviseAttachment 503233